PERMIT #7098602-CN
411 UNIVERSITY ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 17, 2025
In Review
2 cycles
Reviews Done
October 28, 2025
Ready to Issue
October 28, 2025
Issued
October 29, 2025
Completed
February 19, 2026
Expires
April 29, 2027
41
Plan Review Days — Total
27
Plan Review Days — City Control
14
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
411 UNIVERSITY ST, SEATTLE, WA Property
Renovation at 411 UNIVERSITY ST Project
ELEMENTS HOSPITALITY Contractor
Downtown Neighborhood
Project Overview
Project Details
Value
$54,286
Type
Commercial Construction
Issued
October 29, 2025
Location
Downtown
Contractor Information
Location & Map
Project Description
411 University St - Construction Permit Construct interior, non-structural alterations for guestrooms 407 and 409 in commercial hotel building [FAIRMONT OLYMPIC HOTEL], per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ELEMEH*884NZ
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0027823
Review cycles
2
Plan review days
41
Days in corrections
14
Expires
April 29, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0