PERMIT #7098676-CN

2114 NE MASON RD, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
August 26, 2025
In Review
2 cycles
Issued
January 30, 2026
Completed
Expires
July 30, 2027
84
Plan Review Days — Total
36
Plan Review Days — City Control
48
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$124,009
Type
Commercial Construction
Issued
January 30, 2026
Location
University District

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
UW parking Regrade and restripe parking lots C12B and C12C and construct curb ramp, per plans

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Institutional
Parcel
DV0016304
Review cycles
2
Plan review days
84
Days in corrections
48
Expires
July 30, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map