PERMIT #7098680-CN
5317 S HUDSON ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
March 4, 2026
In Review
3 cycles
Reviews Done
June 4, 2026
Ready to Issue
June 5, 2026
Issued
June 5, 2026
Completed
—
Expires
—
92
Plan Review Days — Total
30
Plan Review Days — City Control
62
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
5317 S HUDSON ST, SEATTLE, WA Property
Renovation at 5317 S HUDSON ST Project
Seward Park Neighborhood
Project Overview
Project Details
Value
$311,294
Type
Residential Construction
Issued
June 5, 2026
Location
Seward Park
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct substantial alterations to one family dwelling per plan.
Additional Details
Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0003125
Review cycles
3
Plan review days
92
Days in corrections
62
Units added
0
Units removed
0