PERMIT #7098928-CN

6505 44TH AVE NE, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 9, 2025
In Review
3 cycles
Reviews Done
December 2, 2025
Ready to Issue
December 3, 2025
Issued
December 3, 2025
Completed
June 23, 2026
Expires
June 3, 2027
54
Plan Review Days — Total
51
Plan Review Days — City Control
3
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ravenna Neighborhood

Project Overview

Project Details
Value
$184,038
Type
Residential Construction
Issued
December 3, 2025
Location
Ravenna

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
DANESH DADU Allow new detached accessory dwelling unit to existing single family use per land use code. Construct new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1124416
Review cycles
3
Plan review days
54
Days in corrections
3
Expires
June 3, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map