PERMIT #7098995-CN
2727 WARREN AVE N, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 26, 2025
In Review
3 cycles
Reviews Done
February 27, 2026
Ready to Issue
March 6, 2026
Issued
March 6, 2026
Completed
—
Expires
September 6, 2027
63
Plan Review Days — Total
44
Plan Review Days — City Control
19
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2727 WARREN AVE N, SEATTLE, WA Property
Queen Anne Neighborhood
Project Overview
Project Details
Value
$242,000
Type
Residential Construction
Issued
March 6, 2026
Location
Queen Anne
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
2727 Warren Ave N - Construction Allow new attached accessory dwelling unit to existing single family use per land use code. Construct substantial alterations for a two family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1097782
Review cycles
3
Plan review days
63
Days in corrections
19
Expires
September 6, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0