PERMIT #7099170-CN

2809 W GARFIELD ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 20, 2025
In Review
4 cycles
Reviews Done
March 19, 2026
Ready to Issue
March 20, 2026
Issued
March 20, 2026
Completed
Expires
September 20, 2027
180
Plan Review Days — Total
52
Plan Review Days — City Control
128
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Magnolia Neighborhood

Project Overview

Project Details
Value
$773,613
Type
Residential Construction
Issued
March 20, 2026
Location
Magnolia

Contractor Information

Contractor
SALTWATR CORPORATION
General Contractor
License SALTWC*742BL

Location & Map

Project Description
Construction Permit Construct north one-family dwelling, per plan. (Establish use as single-family residence and detached accessory dwelling unit (DADU), per land use code. Construct (2) one-family dwellings, per plan. Review and processing for two records under 7099170-CN).

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SALTWC*742BL
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1091378
Review cycles
4
Plan review days
180
Days in corrections
128
Expires
September 20, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor