Construction Permit Timeline
Applied
August 13, 2025
In Review
—
Issued
November 13, 2025
Completed
March 6, 2026
Expires
May 13, 2027
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$133,533
Type
Commercial Construction
Issued
November 13, 2025
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Lumen Bio Manufacturing HUB - Phase 3 Construct alterations for lobby at existing commercial building (Lumen Bioscience Manufacturing), per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GTHREBC834LL
Review level
Full +
Primary use
Commercial
Parcel
DV0023572
Expires
May 13, 2027
Existing units
0
Sleeping rooms
0