PERMIT #7099407-CN
7748 25TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 20, 2025
In Review
3 cycles
Reviews Done
March 30, 2026
Ready to Issue
March 31, 2026
Issued
April 10, 2026
Completed
—
Expires
October 10, 2027
161
Plan Review Days — Total
108
Plan Review Days — City Control
53
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$687,410
Type
Residential Construction
Issued
April 10, 2026
Location
Ballard
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Construct west two-family dwelling, per plan. (Establish use as townhouse per land use code. Construct (2) two-family dwellings, per plan. Review and processing for two records under 7099407-CN)
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1120190
Related land-use permit
3043192-LU
Review cycles
3
Plan review days
161
Days in corrections
53
Expires
October 10, 2027
Existing units
1
Units added
2
Units removed
0
Sleeping rooms
0