PERMIT #7099408-DM

7748 25TH AVE NW, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 17, 2025
In Review
2 cycles
Reviews Done
November 12, 2025
Ready to Issue
November 14, 2025
Issued
March 3, 2026
Completed
July 15, 2026
Expires
September 3, 2027
26
Plan Review Days — Total
26
Plan Review Days — City Control
0
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$800,000
Type
Residential Construction
Issued
March 3, 2026
Location
Ballard

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Demolition Permit Demolish single-family dwelling with basement, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1120190
Review cycles
2
Plan review days
26
Days in corrections
0
Expires
September 3, 2027
Open official SDCI detail →
Open Map