PERMIT #7099411-CN

1709 N 105TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 5, 2025
In Review
3 cycles
Reviews Done
May 8, 2026
Ready to Issue
May 13, 2026
Issued
May 13, 2026
Completed
Expires
November 13, 2027
184
Plan Review Days — Total
116
Plan Review Days — City Control
68
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
HOMES WEST INC Contractor
Northgate Neighborhood

Project Overview

Project Details
Value
$380,343
Type
Residential Construction
Issued
May 13, 2026
Location
Northgate

Contractor Information

Contractor
HOMES WEST INC
General Contractor
License HOMESWI864LT

Location & Map

Project Description
(3) New SFR - (No work on ext'g SFR) Construct new west one family dwelling, per plan. (Construct (3) new one family dwellings, per plan. Review and processing for three records under 7099411-CN)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HOMESWI864LT
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0091044
Review cycles
3
Plan review days
184
Days in corrections
68
Expires
November 13, 2027
Existing units
1
Units added
3
Units removed
0
Sleeping rooms
0
Open official SDCI detail →