PERMIT #7099416-GR

2426 E INTERLAKEN BLVD, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
December 2, 2025
In Review
2 cycles
Reviews Done
March 10, 2026
Ready to Issue
March 10, 2026
Issued
March 10, 2026
Completed
June 22, 2026
Expires
September 10, 2027
98
Plan Review Days — Total
43
Plan Review Days — City Control
55
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$10,000
Type
Residential Construction
Issued
March 10, 2026
Location
Capitol Hill

Contractor Information

Contractor
CAMBIUM INC
General Contractor
License CAMBII*020KG

Location & Map

Project Description
rear yard steps and path to garage Construct site work to single family residence, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CAMBII*020KG
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0077912
Review cycles
2
Plan review days
98
Days in corrections
55
Expires
September 10, 2027
Open official SDCI detail →