PERMIT #7099417-CN
2002 10TH AVE E, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 22, 2025
In Review
2 cycles
Reviews Done
December 2, 2025
Ready to Issue
December 18, 2025
Issued
January 8, 2026
Completed
—
Expires
July 8, 2027
41
Plan Review Days — Total
39
Plan Review Days — City Control
2
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$350,000
Type
Residential Construction
Issued
January 8, 2026
Location
Capitol Hill
Contractor Information
Location & Map
Project Description
Ext'g SFR Sub Alt/Add & New basement AADU Allow new attached accessory dwelling unit to existing single family use per land use code. Construct substantial alterations and additions for a two family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SAVVYCD821PB
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1111095
Review cycles
2
Plan review days
41
Days in corrections
2
Expires
July 8, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0