PERMIT #7099594-CN

5233 48TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
August 4, 2025
In Review
Issued
September 4, 2025
Completed
Expires
March 4, 2027
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$88,674
Type
Residential Construction
Issued
September 4, 2025
Location
West Seattle

Contractor Information

Contractor
ORONA CONSTRUCTION LLC
General Contractor
License ORONACL774DA

Location & Map

Project Description
Dunivan Cedar Cottage Allow new Detached Accessory Dwelling Unit to existing single-family residence, per land use code. Construct new one one-family dwelling, per Standard Plan 6800134-SP.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ORONACL774DA
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1135471
Expires
March 4, 2027
Existing units
0
Sleeping rooms
1
Open official SDCI detail →
View Contractor