PERMIT #7099618-CN
1925 4TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 1, 2025
In Review
2 cycles
Reviews Done
November 4, 2025
Ready to Issue
November 5, 2025
Issued
January 30, 2026
Completed
—
Expires
July 30, 2027
34
Plan Review Days — Total
253
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1925 4TH AVE W, SEATTLE, WA Property
Renovation at 1925 4TH AVE W Project
SUNDE BUILDERS LLC Contractor
Queen Anne Neighborhood
Project Overview
Project Details
Value
$400,000
Type
Residential Construction
Issued
January 30, 2026
Location
Queen Anne
Contractor Information
Location & Map
Project Description
Laali Remodel Construct substantial alterations to convert multifamily dwelling to two-family dwelling, per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SUNDEBL893N2
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1211189
Review cycles
2
Plan review days
34
Days in corrections
253
Expires
July 30, 2027
Existing units
2
Units added
0
Units removed
1
Sleeping rooms
6