PERMIT #7099844-CN

1512 ALASKAN WAY, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 11, 2025
In Review
2 cycles
Reviews Done
December 29, 2025
Ready to Issue
December 29, 2025
Issued
December 29, 2025
Completed
Expires
June 29, 2027
18
Plan Review Days — Total
13
Plan Review Days — City Control
5
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$197,020
Type
Commercial Construction
Issued
December 29, 2025
Location
Downtown

Contractor Information

Contractor
CATCH CONSTRUCTION LLC
General Contractor
License CATCHCL805LW

Location & Map

Project Description
Grounded Co Construct tenant improvements to existing commercial building at the ground level east suite ( grounded co.), occupy per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CATCHCL805LW
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0352759
Review cycles
2
Plan review days
18
Days in corrections
5
Expires
June 29, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →