PERMIT #7099895-CN

1209 NE 70TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 15, 2025
In Review
4 cycles
Reviews Done
December 17, 2025
Ready to Issue
December 17, 2025
Issued
December 17, 2025
Completed
Expires
June 17, 2027
63
Plan Review Days — Total
242
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Roosevelt Neighborhood

Project Overview

Project Details
Value
$227,693
Type
Residential Construction
Issued
December 17, 2025
Location
Roosevelt

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
NATE DADU 2 Allow a detached accessory dwelling unit, per land use code. Construct new south one family dwelling, per plan

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0040044
Review cycles
4
Plan review days
63
Days in corrections
242
Expires
June 17, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0