PERMIT #7100082-CN
530 NE 88TH ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
February 3, 2026
In Review
3 cycles
Reviews Done
April 27, 2026
Ready to Issue
April 29, 2026
Issued
April 30, 2026
Completed
—
Expires
October 30, 2027
83
Plan Review Days — Total
54
Plan Review Days — City Control
29
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
530 NE 88TH ST, SEATTLE, WA Property
Maple Leaf Neighborhood
Project Overview
Project Details
Value
$629,902
Type
Residential Construction
Issued
April 30, 2026
Location
Maple Leaf
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Hsiao and Razzak New Home Establish use as single-family residence, per land use code. Construct one-family dwelling, per plan
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1181318
Review cycles
3
Plan review days
83
Days in corrections
29
Expires
October 30, 2027
Existing units
1
Units added
1
Units removed
1
Sleeping rooms
4