PERMIT #7100544-CN

2415 MONTAVISTA PL W, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 5, 2025
In Review
3 cycles
Reviews Done
May 12, 2026
Ready to Issue
May 13, 2026
Issued
May 14, 2026
Completed
Expires
November 14, 2027
188
Plan Review Days — Total
114
Plan Review Days — City Control
74
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$825,899
Type
Residential Construction
Issued
May 14, 2026
Location
Magnolia

Contractor Information

Contractor
MOKAN HOMES LLC
General Contractor
License MOKANHL813BG

Location & Map

Project Description
PK Montavista Establish use as single family residence with attached accessory dwelling unit per land use code. Construct new two-family dwelling per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MOKANHL813BG
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0043909
Review cycles
3
Plan review days
188
Days in corrections
74
Expires
November 14, 2027
Existing units
1
Units added
1
Units removed
1
Sleeping rooms
0
Open official SDCI detail →
View Contractor