PERMIT #7100718-CN
2719 W ELMORE ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 16, 2025
In Review
3 cycles
Reviews Done
July 1, 2026
Ready to Issue
July 1, 2026
Issued
July 1, 2026
Completed
—
Expires
—
197
Plan Review Days — Total
123
Plan Review Days — City Control
74
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$746,879
Type
Residential Construction
Issued
July 1, 2026
Location
Magnolia
Contractor Information
Location & Map
Project Description
Construct new one-family dwelling (North SFR) per plan. (Establish use as single-family residence with detached accessory dwelling unit per Land Use Code. Construct two new one-family dwellings per plan. Review and processing for two records under 7100718-CN.)
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1133926
Review cycles
3
Plan review days
197
Days in corrections
74
Units added
1
Units removed
0