PERMIT #7100749-CN
711 N 35TH ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 22, 2025
In Review
3 cycles
Reviews Done
February 25, 2026
Ready to Issue
February 27, 2026
Issued
February 27, 2026
Completed
—
Expires
August 27, 2027
156
Plan Review Days — Total
66
Plan Review Days — City Control
90
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$30,000
Type
Residential Construction
Issued
February 27, 2026
Location
Fremont
Contractor Information
Contractor
Not published by SDCI
License MASTENS863JS
Location & Map
Project Description
AT&T WA6466 Fremont / LTE 1C RRH Swap Construct alterations to minor telecommunications facility (AT&T) on rooftop of existing commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MASTENS863JS
Review level
Full +
Primary use
Multifamily
Parcel
DV0353518
Review cycles
3
Plan review days
156
Days in corrections
90
Expires
August 27, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0