PERMIT #7100968-CN
6522 42ND AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 12, 2025
In Review
4 cycles
Reviews Done
April 16, 2026
Ready to Issue
April 16, 2026
Issued
April 16, 2026
Completed
—
Expires
October 16, 2027
155
Plan Review Days — Total
88
Plan Review Days — City Control
67
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
6522 42ND AVE NE, SEATTLE, WA Property
Demolition at 6522 42ND AVE NE Project
WINFIELD HOMES LLC Contractor
Ravenna Neighborhood
Project Overview
Project Details
Value
$766,363
Type
Residential Construction
Issued
April 16, 2026
Location
Ravenna
Contractor Information
Location & Map
Project Description
Winfield 6522 42nd Ave NE SFR Construct new one-family dwelling, per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
WINFIHL851D6
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0060597
Review cycles
4
Plan review days
155
Days in corrections
67
Expires
October 16, 2027
Existing units
1
Units added
1
Units removed
1
Sleeping rooms
0