PERMIT #7100970-CN

5039 B 36TH AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 18, 2025
In Review
2 cycles
Reviews Done
January 2, 2026
Ready to Issue
January 5, 2026
Issued
March 1, 2026
Completed
Expires
September 1, 2027
106
Plan Review Days — Total
88
Plan Review Days — City Control
18
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$293,483
Type
Residential Construction
Issued
March 1, 2026
Location
Other Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Construction Permit Construct EAST one-family dwelling, per plan (Establish use and construct 3 single family dwellings, per land use code. Construct as east, center and west one-family dwellings, review and process for three records under 7100970-CN).

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1140822
Review cycles
2
Plan review days
106
Days in corrections
18
Expires
September 1, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map