PERMIT #7100980-CN

12025 22ND AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 15, 2025
In Review
6 cycles
Reviews Done
May 20, 2026
Ready to Issue
May 20, 2026
Issued
May 20, 2026
Completed
Expires
November 20, 2027
247
Plan Review Days — Total
123
Plan Review Days — City Control
124
Days in Applicant Control
6
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$230,928
Type
Residential Construction
Issued
May 20, 2026
Location
Other Seattle

Contractor Information

Contractor
MILLENNIUM GENERAL CONTRACTING
General Contractor
License MILLEGC752BW

Location & Map

Project Description
Kulaga DADU App Allow new detached accessory dwelling unit to existing single family use per land use code. Construct new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MILLEGC752BW
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1099724
Review cycles
6
Plan review days
247
Days in corrections
124
Expires
November 20, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor