PERMIT #7100990-CN

10222 64TH AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 4, 2025
In Review
4 cycles
Reviews Done
May 20, 2026
Ready to Issue
May 26, 2026
Issued
May 26, 2026
Completed
Expires
November 26, 2027
167
Plan Review Days — Total
94
Plan Review Days — City Control
73
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Rainier Beach Neighborhood

Project Overview

Project Details
Value
$748,687
Type
Residential Construction
Issued
May 26, 2026
Location
Rainier Beach

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Ext'g SFR Sub Alt Construct substantial alterations and additions for one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0038829
Review cycles
4
Plan review days
167
Days in corrections
73
Expires
November 26, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map