PERMIT #7101045-CN

5862 MCKINLEY PL N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 25, 2025
In Review
4 cycles
Reviews Done
April 27, 2026
Ready to Issue
April 27, 2026
Issued
April 27, 2026
Completed
Expires
October 27, 2027
153
Plan Review Days — Total
72
Plan Review Days — City Control
81
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Green Lake Neighborhood

Project Overview

Project Details
Value
$190,000
Type
Residential Construction
Issued
April 27, 2026
Location
Green Lake

Contractor Information

Contractor
TOPAZ REMODELING INC
General Contractor
License TOPAZRI777OA

Location & Map

Project Description
5862 McKinley Pl N - Basement Renovation Construct addition and alterations to existing one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
TOPAZRI777OA
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0057983
Review cycles
4
Plan review days
153
Days in corrections
81
Expires
October 27, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →