PERMIT #7101065-CN

2724 WALNUT AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 24, 2025
In Review
3 cycles
Reviews Done
May 27, 2026
Ready to Issue
May 28, 2026
Issued
June 3, 2026
Completed
Expires
154
Plan Review Days — Total
122
Plan Review Days — City Control
32
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$964,796
Type
Residential Construction
Issued
June 3, 2026
Location
West Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Establish use as townhouse per land use code. Construct new two family dwelling per plan.

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1092152
Related land-use permit
3043227-LU
Review cycles
3
Plan review days
154
Days in corrections
32
Units added
2
Units removed
0
Open Map