PERMIT #7101410-CN
1816 24TH AVE E, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 12, 2025
In Review
4 cycles
Reviews Done
June 24, 2026
Ready to Issue
June 24, 2026
Issued
June 24, 2026
Completed
—
Expires
—
224
Plan Review Days — Total
107
Plan Review Days — City Control
117
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1816 24TH AVE E, SEATTLE, WA Property
Capitol Hill Neighborhood
Project Overview
Project Details
Value
$211,154
Type
Residential Construction
Issued
June 24, 2026
Location
Capitol Hill
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct additions and alterations to convert one-family dwelling to two-family dwelling per plan. Establish use as a single family residence with attached accessory dwelling unit (AADU) per the Land Use Code.
Additional Details
Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0017030
Review cycles
4
Plan review days
224
Days in corrections
117
Units added
1
Units removed
0