PERMIT #7101472-CN
3051 44TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 8, 2026
In Review
3 cycles
Reviews Done
February 17, 2026
Ready to Issue
February 17, 2026
Issued
February 17, 2026
Completed
—
Expires
August 17, 2027
40
Plan Review Days — Total
33
Plan Review Days — City Control
7
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
3051 44TH AVE W, SEATTLE, WA Property
Magnolia Neighborhood
Project Overview
Project Details
Value
$10,000
Type
Residential Construction
Issued
February 17, 2026
Location
Magnolia
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Construct foundation repairs to one-family dwelling, per plan
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1171421
Review cycles
3
Plan review days
40
Days in corrections
7
Expires
August 17, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0