PERMIT #7101525-CN

5053 A 25TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 15, 2025
In Review
3 cycles
Reviews Done
April 23, 2026
Ready to Issue
April 23, 2026
Issued
July 7, 2026
Completed
Expires
129
Plan Review Days — Total
111
Plan Review Days — City Control
18
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$358,422
Type
Residential Construction
Issued
July 7, 2026
Location
West Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct east one-family dwelling (SFR1) per plan. (Establish use as single-family residence per land use code. Construct (2) one-family dwellings and one duplex per plan. Review and processing for three records under 7101525-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1110563
Review cycles
3
Plan review days
129
Days in corrections
18
Units added
3
Units removed
1
Open Map