PERMIT #7101683-CN

4430 A S HOLLY ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 19, 2025
In Review
3 cycles
Reviews Done
May 18, 2026
Ready to Issue
May 18, 2026
Issued
May 26, 2026
Completed
Expires
November 26, 2027
180
Plan Review Days — Total
107
Plan Review Days — City Control
73
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$680,880
Type
Residential Construction
Issued
May 26, 2026
Location
Rainier Valley

Contractor Information

Contractor
ROSE HOMES GC LLC
General Contractor
License ROSEHHG797DS

Location & Map

Project Description
Construction Permit Construct WEST DPLX, per plan [Allow for 4 additional residential townhouse units, per land use code. Construct as west and east two-family dwelling (DPLX.); review and process for two records under 7101683-CN] Existing residence to remain.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ROSEHHG797DS
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1098442
Review cycles
3
Plan review days
180
Days in corrections
73
Expires
November 26, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor