PERMIT #7101779-CN

1915 10TH AVE E, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
March 31, 2026
In Review
2 cycles
Reviews Done
May 20, 2026
Ready to Issue
May 21, 2026
Issued
May 21, 2026
Completed
Expires
November 21, 2027
50
Plan Review Days — Total
29
Plan Review Days — City Control
21
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Eastlake Neighborhood

Project Overview

Project Details
Value
$233,756
Type
Residential Construction
Issued
May 21, 2026
Location
Eastlake

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Fasola - Addition & AADU Allow housing for one new stacked dwelling unit within an existing structure, per land use code. Construct addition & alterations to convert one-family dwelling to two-family dwelling, per plan

Additional Details

Permit Intelligence
Work performed by
Other Exemption from RCW 18.27.090
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0059640
Review cycles
2
Plan review days
50
Days in corrections
21
Expires
November 21, 2027
Existing units
0
Units added
2
Units removed
1
Sleeping rooms
0
Open official SDCI detail →
Open Map