PERMIT #7101795-CN
12527 A 39TH AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
August 14, 2025
In Review
0 cycles
Issued
March 17, 2026
Completed
—
Expires
September 17, 2027
202
Plan Review Days — Total
202
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$489,311
Type
Residential Construction
Issued
March 17, 2026
Location
Lake City
Contractor Information
Location & Map
Project Description
CEDAR PARK HOMES SITE B NE SE NW SW Construct NW SFR 3 per plans (Establish use as single-family residences per he land use code. Construct (4) one-family dwellings per plans. Reviews and processing for (4) -CN's under 7075424)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
OLSENAC813OC
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1157477
Review cycles
0
Plan review days
202
Days in corrections
0
Expires
September 17, 2027