PERMIT #7102018-CN

13540 B 25TH AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 3, 2025
In Review
3 cycles
Reviews Done
January 5, 2026
Ready to Issue
January 5, 2026
Issued
January 5, 2026
Completed
Expires
July 5, 2027
94
Plan Review Days — Total
53
Plan Review Days — City Control
41
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$232,862
Type
Residential Construction
Issued
January 5, 2026
Location
Pinehurst

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
NEW SFR Construct new one family dwelling, per plan. Remove existing detached garage.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1160691
Review cycles
3
Plan review days
94
Days in corrections
41
Expires
July 5, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
3
Open official SDCI detail →
Open Map