PERMIT #7102278-CN
301 W NICKERSON ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 26, 2025
In Review
4 cycles
Reviews Done
July 17, 2026
Ready to Issue
July 21, 2026
Issued
July 21, 2026
Completed
—
Expires
—
233
Plan Review Days — Total
88
Plan Review Days — City Control
145
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
301 W NICKERSON ST, SEATTLE, WA Property
Fremont Neighborhood
Project Overview
Project Details
Value
$1,278,079
Type
Commercial Construction
Issued
July 21, 2026
Location
Fremont
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Change of use from Sales and services general to restaurant per land use code. Construct alterations for restaurant (Chipotle) and occupy per plan. Mechanical included in this permit.
Additional Details
Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0065858
Review cycles
4
Plan review days
233
Days in corrections
145
Units added
0
Units removed
0