PERMIT #7102493-CN

6027 B 4TH AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 25, 2025
In Review
3 cycles
Reviews Done
April 15, 2026
Ready to Issue
April 16, 2026
Issued
May 21, 2026
Completed
Expires
November 21, 2027
111
Plan Review Days — Total
86
Plan Review Days — City Control
25
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$344,136
Type
Residential Construction
Issued
May 21, 2026
Location
Roosevelt

Contractor Information

Contractor
Vivid Development LLC
Single Family/Duplex
License VIVIDDL801B4

Location & Map

Project Description
2 New SFRs + New Duplex - Construction Permit Construct new one family dwelling (NE – SFR1), per plan. (Establish use as (2) single-family residences and (1) townhouse, per land use code. Construct (2) new one-family dwellings and (1) new two-family dwelling, per plan. Review and processing for three records under 7102493-CN.)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VIVIDDL801B4
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1116583
Related land-use permit
3043270-LU
Review cycles
3
Plan review days
111
Days in corrections
25
Expires
November 21, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →