PERMIT #7102643-CN

400 PINE ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
December 17, 2025
In Review
1 cycle
Reviews Done
December 26, 2025
Ready to Issue
December 26, 2025
Issued
December 29, 2025
Completed
May 15, 2026
Expires
June 29, 2027
9
Plan Review Days — Total
9
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$53,164
Type
Commercial Construction
Issued
December 29, 2025
Location
Downtown

Contractor Information

Contractor
MICHIGAN WOODS CONST INC
General Contractor
License MICHIWC852RU

Location & Map

Project Description
N016 Shoes Tenant improvements for retail store (Nordstrom Rack) at basement of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MICHIWC852RU
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0008454
Review cycles
1
Plan review days
9
Days in corrections
0
Expires
June 29, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor