PERMIT #7102710-CN
1408 NW 63RD ST, SEATTLE, WA
newPermit Timeline & Status
Construction Permit Timeline
Applied
October 29, 2025
In Review
3 cycles
Reviews Done
February 10, 2026
Ready to Issue
February 11, 2026
Issued
—
Completed
—
Expires
—
104
Plan Review Days — Total
39
Plan Review Days — City Control
65
Days in Applicant Control
3
Review Cycles
Plan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$42,000
Type
Residential Construction
Issued
N/A
Location
Ballard
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct alterations to replace exterior stairs and balconies of existing multi-family building per plan
Additional Details
Permit Intelligence
Review level
Full +
Primary use
Multifamily
Parcel
DV1153833
Review cycles
3
Plan review days
104
Days in corrections
65
Units added
0
Units removed
0