PERMIT #7102923-CN

5801 GREENWOOD AVE N, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
December 3, 2025
In Review
3 cycles
Reviews Done
June 15, 2026
Ready to Issue
June 17, 2026
Issued
Completed
Expires
194
Plan Review Days — Total
113
Plan Review Days — City Control
81
Days in Applicant Control
3
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$728,733
Type
Residential Construction
Issued
N/A
Location
Phinney Ridge

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new two-family dwelling per plan. (Establish use as housing for two attached dwelling units and one detached dwelling unit per land use code. Construct new one- and two-family dwellings per plan. Review and processing for two records under 7102923-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1117207
Related land-use permit
3043276-LU
Review cycles
3
Plan review days
194
Days in corrections
81
Units added
2
Units removed
0
Open Map