PERMIT #7103024-CN
1520 15TH AVE E, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 4, 2025
In Review
3 cycles
Issued
December 16, 2025
Completed
—
Expires
June 16, 2027
103
Plan Review Days — Total
29
Plan Review Days — City Control
74
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$25,000
Type
Residential Construction
Issued
December 16, 2025
Location
Capitol Hill
Contractor Information
Contractor
Not published by SDCI
License MASTENS863JS
Location & Map
Project Description
1520 15th Ave E - Construction - SG34 CAPITOL HILL GALER AT&T RRH SWAP Construct alterations to minor telecommunications facility [AT&T] at rooftop and ground level equipment room of multi-family building [PARKE GRANDVIEW CONDOMINIUM], per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MASTENS863JS
Review level
Full +
Primary use
Multifamily
Parcel
DV0064894
Review cycles
3
Plan review days
103
Days in corrections
74
Expires
June 16, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0