PERMIT #7103236-CN
1417 4TH AVE, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 15, 2025
In Review
2 cycles
Reviews Done
October 21, 2025
Ready to Issue
October 21, 2025
Issued
October 21, 2025
Completed
February 25, 2026
Expires
April 21, 2027
36
Plan Review Days — Total
24
Plan Review Days — City Control
12
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1417 4TH AVE, SEATTLE, WA Property
Renovation at 1417 4TH AVE Project
METIS CONSTRUCTION INC Contractor
Downtown Neighborhood
Project Overview
Project Details
Value
$244,250
Type
Commercial Construction
Issued
October 21, 2025
Location
Downtown
Contractor Information
Location & Map
Project Description
Escape Room Change of use from office to indoor participant sports, per land use code. Construct alterations to portion of existing office, occupy per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
METISCI910K9
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV0027770
Review cycles
2
Plan review days
36
Days in corrections
12
Expires
April 21, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0