PERMIT #7103440-CN

503 W HIGHLAND DR, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
August 26, 2025
In Review
0 cycles
Issued
April 8, 2026
Completed
Expires
October 8, 2027
218
Plan Review Days — Total
218
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$158,160
Type
Residential Construction
Issued
April 8, 2026
Location
Queen Anne

Contractor Information

Contractor
KREKOW JENNINGS INC
General Contractor
License KREKOJI110BZ

Location & Map

Project Description
503 W Highland Drive Pre-Application Construct new south one-family dwelling, per plan. (Establish use as single family residence with detached accessory dwelling unit, per land use code. Construct two new one-family dwellings, per plan. Review and processing for two records under 7096796)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
KREKOJI110BZ
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV0004059
Review cycles
0
Plan review days
218
Days in corrections
0
Expires
October 8, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor