PERMIT #7103564-CN

215 N 58TH ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 15, 2025
In Review
2 cycles
Reviews Done
October 22, 2025
Ready to Issue
October 23, 2025
Issued
October 23, 2025
Completed
February 20, 2026
Expires
April 23, 2027
37
Plan Review Days — Total
31
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
V&A BUILT Contractor
Phinney Ridge Neighborhood

Project Overview

Project Details
Value
$276,545
Type
Residential Construction
Issued
October 23, 2025
Location
Phinney Ridge

Contractor Information

Contractor
V&A BUILT
General Contractor
License VBUILB*755OD

Location & Map

Project Description
Sub Alt + Add to Exist SFR Construct substantial alterations and upper level additions to existing 1-family dwelling, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VBUILB*755OD
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1186496
Review cycles
2
Plan review days
37
Days in corrections
6
Expires
April 23, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor