PERMIT #7103682-CN
1901 41ST AVE SW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 19, 2025
In Review
3 cycles
Reviews Done
March 17, 2026
Ready to Issue
March 17, 2026
Issued
March 31, 2026
Completed
—
Expires
September 30, 2027
88
Plan Review Days — Total
60
Plan Review Days — City Control
28
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1901 41ST AVE SW, SEATTLE, WA Property
Renovation at 1901 41ST AVE SW Project
PLUM PROJECTS LLC Contractor
West Seattle Neighborhood
Project Overview
Project Details
Value
$950,000
Type
Residential Construction
Issued
March 31, 2026
Location
West Seattle
Contractor Information
Location & Map
Project Description
Construction Permit: Sub alt to SFR Construct additions and substantial alterations to one-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PLUMPPL904DK
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1195909
Review cycles
3
Plan review days
88
Days in corrections
28
Expires
September 30, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0