PERMIT #7104010-CN

1500 N 125TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
February 20, 2026
In Review
3 cycles
Reviews Done
June 17, 2026
Ready to Issue
June 17, 2026
Issued
June 17, 2026
Completed
Expires
117
Plan Review Days — Total
94
Plan Review Days — City Control
23
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Bitter Lake Neighborhood

Project Overview

Project Details
Value
$262,229
Type
Residential Construction
Issued
June 17, 2026
Location
Bitter Lake

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct west one-family dwelling per plan. Remove existing detached garage. (Allow housing for two new detached dwelling unit per land use code. Construct (2) one-family dwellings per plan. Review and processing for two records under 7104010-CN).

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1197624
Review cycles
3
Plan review days
117
Days in corrections
23
Units added
1
Units removed
0
Open Map