PERMIT #7104063-CN

509 NE NORTHLAKE WAY, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 23, 2025
In Review
3 cycles
Reviews Done
May 5, 2026
Ready to Issue
May 6, 2026
Issued
May 6, 2026
Completed
Expires
November 6, 2027
224
Plan Review Days — Total
65
Plan Review Days — City Control
159
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$40,292
Type
Industrial Construction
Issued
May 6, 2026
Location
Wallingford

Contractor Information

Contractor
SELLEN CONSTR CO INC
General Contractor
License SELLEC*372N0

Location & Map

Project Description
Chihuly Studio: Add/Alts Construct alterations and addition to a mixed-use building, per plans

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SELLEC*372N0
Review level
Full +
Primary use
Industrial
Parcel
DV0013610
Review cycles
3
Plan review days
224
Days in corrections
159
Expires
November 6, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →