PERMIT #7104158-CN

1025 S ELMGROVE ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 18, 2025
In Review
3 cycles
Reviews Done
November 6, 2025
Ready to Issue
November 7, 2025
Issued
November 7, 2025
Completed
January 6, 2026
Expires
May 7, 2027
49
Plan Review Days — Total
26
Plan Review Days — City Control
23
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
MR RACKS LLC Contractor
South Park Neighborhood

Project Overview

Project Details
Value
$14,256
Type
Commercial Construction
Issued
November 7, 2025
Location
South Park

Contractor Information

Contractor
MR RACKS LLC
General Contractor
License MRRACRL924BN

Location & Map

Project Description
National Products 1025 Racking Construct alterations to pallet racking within existing warehouse building, (National Products Inc.), per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MRRACRL924BN
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0002362
Review cycles
3
Plan review days
49
Days in corrections
23
Expires
May 7, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor