PERMIT #7104193-DM
5021 FAUNTLEROY WAY SW, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 26, 2025
In Review
2 cycles
Reviews Done
November 28, 2025
Ready to Issue
February 12, 2026
Issued
February 13, 2026
Completed
June 22, 2026
Expires
August 13, 2027
63
Plan Review Days — Total
27
Plan Review Days — City Control
36
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
5021 FAUNTLEROY WAY SW, SEATTLE, WA Property
West Seattle Neighborhood
Project Overview
Project Details
Value
$600,000
Type
Residential Construction
Issued
February 13, 2026
Location
West Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
5021 - Demo PASV Demolish existing two-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1105477
Review cycles
2
Plan review days
63
Days in corrections
36
Expires
August 13, 2027