PERMIT #7104326-CN

2655 NW 63RD ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
August 29, 2025
In Review
2 cycles
Issued
December 1, 2025
Completed
December 15, 2025
Expires
June 1, 2027
87
Plan Review Days — Total
22
Plan Review Days — City Control
65
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$20,000
Type
Residential Construction
Issued
December 1, 2025
Location
Ballard

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Seismic Retrofit Construct Earthquake Home Retrofit Prescriptive plan, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0057351
Review cycles
2
Plan review days
87
Days in corrections
65
Expires
June 1, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
3
Open official SDCI detail →
Open Map