PERMIT #7105030-CN
8022 30TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 17, 2025
In Review
3 cycles
Reviews Done
May 15, 2026
Ready to Issue
May 18, 2026
Issued
May 18, 2026
Completed
—
Expires
November 18, 2027
210
Plan Review Days — Total
52
Plan Review Days — City Control
158
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
8022 30TH AVE NW, SEATTLE, WA Property
Addition at 8022 30TH AVE NW Project
2M RESIDENTIAL LLC Contractor
Ballard Neighborhood
Project Overview
Project Details
Value
$41,942
Type
Residential Construction
Issued
May 18, 2026
Location
Ballard
Contractor Information
Location & Map
Project Description
Henry Doan Construct addition and alterations to existing one family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
2MRESRL777QL
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0074390
Review cycles
3
Plan review days
210
Days in corrections
158
Expires
November 18, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0