PERMIT #7105088-CN
220 NE 120TH ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 1, 2025
In Review
2 cycles
Reviews Done
October 30, 2025
Ready to Issue
November 3, 2025
Issued
November 3, 2025
Completed
—
Expires
May 3, 2027
29
Plan Review Days — Total
28
Plan Review Days — City Control
1
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$184,613
Type
Residential Construction
Issued
November 3, 2025
Location
Northgate
Contractor Information
Location & Map
Project Description
Baldner Sedge Cottage Allow new Detached Accessory Dwelling Unit to existing single-family residence, per land use code. Construct new one-family dwelling, per Standard Plan 7061680-SP
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BALDNSL762RF
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1201921
Review cycles
2
Plan review days
29
Days in corrections
1
Expires
May 3, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
2